Turning an Assessment into an Estimate

Once an assessment is complete, you can generate a draft estimate from it. The technician's findings and recommended work carry over as text for the customer, and only the assessment fee is added as a line. You then price the actual work on the estimate. The fee can be credited back so the customer is not charged twice.

Before you start

  • You need both permission to record assessment outcomes and permission to create estimates. Without both, the page says so instead of showing the form.
  • The assessment must be completed, have at least one finding, and not have produced an estimate already.
  • If the assessment was cancelled, no estimate can be generated from it.

Steps

  1. Open the completed assessment and find Estimate Generation.
  2. Set Valid Until with the date picker.
  3. Review Sales tax. It is calculated from the service address and your tax jurisdictions when the estimate is generated. Manage tax jurisdictions opens that setup.
  4. Optionally edit Customer Notes Override and Internal Notes Override.
  5. If the assessment has a fee, answer Credit the assessment fee if the customer accepts this estimate. It starts ticked or unticked from your company setting Credit Assessment Fees by Default, and you can change it for this estimate. The fee is always added to the estimate as a line. If the assessment has no fee, this question does not appear.
  6. Select Generate Draft Estimate. You are taken to the new estimate to price the work.

If an estimate already exists, the section says This assessment already generated an estimate with an Open estimate link. If the outcome has not been recorded, it says to record the outcome first.

What carries over

The findings and recommended work appear in the estimate's customer-facing Diagnosis & Recommended Work section. They are not line items, and the assessment's pricing is not copied.

Absorbing the assessment fee

When the customer accepts the estimate, the fee can be credited back as a negative line, so the customer pays for the work rather than for the visit and the work. Your answer to Credit the assessment fee if the customer accepts this estimate decides, and it is saved on the estimate:

  • If you chose to credit it, the fee is credited when the customer accepts, however they accept: through their portal, a guest link, or with you recording it. The estimate shows Assessment Fee Absorption and the total with the credit.
  • If you did not, the fee is charged on the estimate and not credited. The estimate says so.

The company setting Credit Assessment Fees by Default only sets the starting answer. An estimate created any other way, for example from a booked job, charges the fee and does not credit it. To credit the customer later, reverse the fee line on the estimate.

Absorption is a permission of its own, and it is refused for an estimate that has already been converted. The estimate page also lets you waive the fee line on a draft estimate if you have permission.

Tips

  • If you invoiced the assessment fee separately and then also keep the fee line, the customer is billed for it twice. Pick one route.
  • For sending, approval and conversion to work orders, see the linked estimate guides.

If something goes wrong

  • If Generate Draft Estimate reports it could not generate yet, confirm the assessment is completed and has findings and recommended work.
  • If the fee did not credit, open the estimate: the Assessment Fee Absorption panel says whether it was set to be credited. Check that the estimate is linked to this assessment.

Related articles

  • How Assessments Work — An assessment is a visit to look at the work before a price is committed to. It belongs to a Job, is carried out by a technician on site, and can carry a fee. When the visit is finished the technician…
  • Scheduling an Assessment and Handling Its Fee — You schedule an assessment from a Job. It records the customer, the Property, a time and an optional fee taken from your pricebook. After the visit, the fee is either invoiced on its own, waived, or…
  • Recording Findings and Choosing an Outcome — On site, the technician starts the assessment, describes what they found, adds photos, and then completes the visit by choosing a result. Walter AI can help draft structured details and a diagnosis…
  • Absorb an Assessment Fee — When an estimate is generated from an assessment that still has an outstanding fee, that fee can be absorbed into the estimate instead of being billed on its own. Absorption happens when the estimate…
  • Create an Estimate — Creating an estimate lets you put a quote in front of a customer before the work starts. An estimate is written for a specific job, customer and Property, and it holds the line items you are…
  • How Estimate Approval Works — An estimate is only useful if the customer's yes is something you can point to later. ServiceVisit treats acceptance as a record, not a status change: when a customer approves, the system keeps what…

Still need a hand?

Email our support team and a person will get back to you.

ServiceVisit Sales

Pre-sales questions? Ask away.

Walter is an AI assistant and can make mistakes. Don’t share passwords or card details.

Sales is offline.

Say hello to get started.

This chat has ended.

The conversation is saved for both you and the Sales team.